Q9. In matrix organization structure, usually employees have two bosses to whom they may have to report. A project manager in a matrix organization has been assigned to construct a multi storied commercial complex. The project manager has visited the functional manager to confirm the required resources for project. He should manage and lead the project team effectively to meet the project objectives. What should the project manager do for the effective management of project team?

Improving competencies, team interaction and overall team environment.

Tracking team member performance, giving recognition and reward and providing feedback to optimize project performance.

Confirming human resource availability and obtaining necessary team to complete project activities

Identifying and documenting project roles and responsibilities, required skills and reporting relationship.

Your Answer =

Answer / Explanation: