Q8. XYZ Developer Company appointed Zackery as the project manager for building a school building in Berlin in the middle of implementation. He looked at the project best practices of comparable projects for gathering knowledge for quality issues. Now, he is analyzing a chart of problems to find out most frequent one in order to determine if the process need to be improved. What project management process he is working with?

Plan quality

Perform quality Control

Benchmarking

Perform quality assurance



Your Answer =


Answer / Explanation: