Q7. An experience project manager is working with his team with project management plan, project finding requirements and work performance data. They looked at historical information of the other project at this process where team used earn value management, forecasting and TCPI technique. The project manager advices his teams to use project management software to obtain cost forecast. Which process the project is in now?

Determine budget

Control cost

Work performance information

Estimate budget



Your Answer =


Answer / Explanation: