Q7. An experience project manager is working with his team with project management plan, project finding requirements and work performance data. They looked at historical information of the other project at this process where team used earn value management, forecasting and TCPI technique. The project manager advices his teams to use project management software to obtain cost forecast. Which process the project is in now?

Determine budget

Control cost

Work performance information

Estimate budget

Your Answer =

Answer / Explanation:

Certexams.com Facebook Page Certexams.com Twitter Page Certexams.com Google+ Page

Disclaimer: PMP™ is trademark of Program Management Institute (PMI) and duly acknowledged. The practice tests material is a copyright of CertExams.com and the same is not approved or endorsed by respective certifying bodies.

Web Analytics

Clicky