Register Login

Home >PMP>Question-2

  Practice Questions  |  Download Practice Tests

PMP™ Practice Questions

Previous    Next

Q2.A project manager in an infrastructure development company is in the process of defining, preparing and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. Which of the below document is not a content of project management plan?


Plan for how processes that are used in the project will be improved

How requirements will be managed and controlled on the project

All the sub plans

Plan for managing changes

Your Answer =

Answer / Explanation:

Disclaimer: PMP™ is trademark of Program Management Institute (PMI) and duly acknowledged. The practice tests material is a copyright of CertExams.com and the same is not approved or endorsed by respective certifying bodies.

Real Time Web Analytics

Clicky