Register Login

Home >PMP >Question-1

  Practice Questions  |  Download Practice Tests

PMP™ Practice Questions

Next

Q1.Robin, the project manager for CID Corporation is working as a project manager. One of the senior functional managers instructed him to work for the upcoming project. Robin told the manager it is not a project but an operational work because __________.

Ongoing and repetitive

Constrained by limited resources

Planned, executed, and controlled

Creates a unique product or service

Your Answer =

Answer / Explanation:

Disclaimer: PMP™ is trademark of Program Management Institute (PMI) and duly acknowledged. The practice tests material is a copyright of CertExams.com and the same is not approved or endorsed by respective certifying bodies.

Real Time Web Analytics

Clicky