Q1.Robin, the project manager for CID Corporation is working as a project manager. One of the senior functional managers instructed him to work for the upcoming project. Robin told the manager it is not a project but an operational work because __________.

Ongoing and repetitive

Constrained by limited resources

Planned, executed, and controlled

Creates a unique product or service

Your Answer =

Answer / Explanation: