Q4.Dividing complex projects to simpler and manageable tasks is the process identified as Work Breakdown Structure. Usually, the project managers use this method for simplifying the project execution. Project managers need to understand the reason of breaking structure. Which of the below choice is not a reason of breaking project work?

Helps to create project charter

Accurate assignment of responsibilities to the project team

Indicates the project milestones and control points

Helps to estimate the cost, time, and risk



Your Answer =


Answer / Explanation: