Q3.Monitor & Control Project Work processes constantly monitor the project for changes, and take the appropriate action whenever you make a change to meet the performance objectives defined in the project management plan. Which of the following is not an output of Monitor & Control Project Work?

Project management plan updates

Change request status updates

Project document updates

Change requests



Your Answer =


Answer / Explanation: